Background

The Solaire Holman project in Brewster County, Texas, is ENGIE SOlAR's first project in ERCOT. The 50 MW single-axis-tracking PV array consists of twenty-six (26) KACO BluePlanet 2200 TL3 skid-mounted power stations. The project's Point of Interconnection (POI) is American Electric Power’s 69 kV Alpine to Fort Stockton transmission line.

The initial POI is a temporary line tap, and six months after COD, the POI will shift to a new AEP switching station connecting the Alpine to Fort Stockton and the Alpine to Barilla Junction transmission lines. 

Approach

First, EPE performed a transmission export analysis for this project and kicked off the interconnection process with the Electric Reliability Council of Texas (ERCOT). EPE modeled two SO MW phases each connecting to separate 69kV circuits as well as connecting to both circuits through a new switching station. On behalf of the client, EPE prepared the necessary applications, studies.

Secondly, EPE developed specifications for the step-up transformer and for the substation EPC solicitation, evaluated bids and advised the client in negotiating and awarding contracts. EPE served as owner's engineer, working with the engineer-ofrecord, providing technical support and reviewing all calculations, drawings and studies. EPE was responsible to ensure that the project complies with interconnection standards for AEP, ERCOT and good utility practice. 

Transmission line image
Single Testimonial Line Mesh
"Technical support from the EPE team was invaluable. The interface with our project partners was seamless, and the interconnection process was effortless."
Matt Held, VP Asset Development, Engie Solar

EPE provided the following services for this project:

  • Full Transmission Export Analysis 
  • ERCOT Interconnection Study Applications 
  • AEP Aspen Model and Interconnection Study Data 
  • Main Power Transformer Specifications 
  • Substation Specifications 
  • Bid Evaluation and Contract Award Support 
  • Reactive Power Compensation Study 
  • Full Registration RARF and ERCOT Registration Support 
  • Desktop Review of Design Drawings and Design System Studies 
  • Supervision of MPT Testing 
  • Substation/Interconnection Facilities Electrical Inspection 
  • Solar Plant Collector System Walk Through 
  • ERCOT Commissioning Plan
  • ERCOT New Generator Commissioning Checklist Assistance 
  • Lead the Lagging/Leading reactive power tests, Primary Frequency Response and Automatic Voltage Regulator Tests 
  • Miscellaneous Technical Support
Transmission line image

Outcome

EPE led this project from the planning phase to the design/engineering/ procurement phase, all the way to getting the project shovel ready and acted as owner's engineer throughout the construction phase. The project energized in March 2017 and began commercial operation in April 2017. The project made a final permanent interconnection in October 2017. 

Want to learn more about our solutions?

When you partner with EPE, you get an experienced team dedicated to providing you with tailored solutions and expert guidance.

Please fill out the form to the right, and a member of our team will be in touch.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.